单项选择题
Team selection is not just a function of finding someone whos a technical or administrative expert. What will a project sponsor leading a high visibility project look for in a project manager?()
A.Developing key personnel
B.Leading technical specialists
C.Interfacing with customers / sponsors
D.Analyzing skills
点击查看答案
相关考题
-
单项选择题
Whydoesaprojectmanagerneedanexecutivesponsor?()
A.To keep the project team focused on its work
B.To provide behind-the-scenes assistance with organizational commitment and support
C.To sign-off on user requirements
D.To negotiate contracts with outside vendors -
单项选择题
Theprojectmanagerisdevelopingaprojectschedule.Theprojectmanagernegotiatedwithalltheexecutionorganizations,andthetasktimesareasshortaspossible.Aftermanipulatingtheschedule,theprojectcompletiondateisstillbeyondthedaterequestedbythebusinessownersoftheproject.Theprojectmanagerbelievesthatthecontentagreedonfortheprojectisappropriate,andconcludesthatthisscheduleshouldbetakentothebusinessownersandrenegotiated.Whichoneofthefollowingtoolswillhelptheprojectmanagerjustifytherevisedschedule?()
A.Data flow model
B.The project critical path
C.Resource loading chart
D.WBS (Work Breakdown Structure) -
单项选择题
WhatistheMOSTaccuratewaytodetermineaproject’sdurationbeforeexecution?()
A.The project manager performs all estimates
B.Incorporate each individual worker’s estimates
C.Acquire expert estimates
D.There is no way to determine the duration