A customer has one IBM System Storage DS8700 in their main data center with one DS6800 at a secondary site. They are using the Global Copy feature between the sites. They want to bring up a test image at the secondary site using the primary site data.
Which sequence of actions will properly bring up the secondary site?()

    A. bring up the secondary site on the target disks
    B. suspend and bring up the secondary site on the target disks
    C. perform a FlashCopy and bring up the secondary site on the target disks
    D. "go-to-sync", perform aFlashCopy, and bring up the secondary site on the target disks