Using the reports server how would you force the orders report in the orders entry application to run every six hours?()

    A.Schedule the report's execution in the queue manager. 
    B.Schedule the reports execution using the R30RQM command line with scheduled parameter. 
    C.Create a trigger in the application to execute the report every six hours. 
    D.You cannot schedule a reports execution.