单项选择题
If the organizational spending plan has allocated $100,000 for a project, and the high level budget estimate for that project is $200,000; which of the following is accurate?()
A.The high level budget estimates are inaccurate
B.The organizational spending plan is inaccurate
C.The budget is not aligned with the spending plan of the organization
D.The detailed bottom up budget will need to be adjusted
点击查看答案
相关考题
-
单项选择题
Whatistheroleofthelinemanagerinaprojectplan?()
A.Provide resources to a project
B.Request requirements changes
C.Resolve team conflicts
D.Control the project budget -
单项选择题
Teammemberlisting,scheduledtasks,andriskidentificationarepartofthe:()
A.project plan.
B.project charter.
C.communication plan.
D.WBS (Work Breakdown Structure). -
单项选择题
Whyisitimportanttohaveafinalmeetingonaprojectthathasbeencancelled?()
A.Document lessons learned
B.Assign responsibility
C.Close budget
D.Begin new project